How to make a PERT chart

A PERT chart maps tasks, estimates and the critical path. Learn the three-point formula, the forward and backward pass, and how to read a finish date.

Written by
FlowDraw Team
Published
Reading time
7 min read
A FlowDraw board with a PERT chart for a trade show booth: nine linked task boxes from Start to Finish, with the critical path drawn in red.

The show opens on May 4 and the booth has to be there. Nobody knows how long the demo app will really take. A PERT chart turns that doubt into a finish date, and shows which tasks can’t slip.

Quick Answer

A PERT chart is a network of tasks with estimates. Give each task optimistic, most likely and pessimistic times, link tasks in order, then calculate each one’s earliest and latest dates. Tasks with no slack form the critical path, which sets the finish date.

What is a PERT chart?

PERT stands for Program Evaluation and Review Technique. The US Navy developed it in the late 1950s for the Polaris missile program, where durations were hard to predict. The example plans a trade show booth.

The first part of a PERT chart for a trade show booth, with numbered pins on Start, a task box, a normal arrow and a red critical arrow.
Tasks are boxes and arrows show what comes first
  1. Start and finish: the two ends of the network, here Apr 5 and May 3.
  2. Task: one box, with its dates inside.
  3. Dependency: an arrow from a task that must finish first.
  4. Critical path: the red route, where any delay moves the finish.

Older PERT charts drew tasks on the arrows. Today most, like this one, put them in boxes.

Use one when durations are uncertain and many tasks run side by side. For tracking dates week by week, a Gantt chart is easier to read.

How to make a PERT chart

Estimate each task

Start with a task list, such as the work packages from a work breakdown structure. Ask the person doing each task for three numbers, in the same unit.

A table of nine tasks, A to I, with optimistic, most likely and pessimistic days, the expected days and which tasks come first.
Three estimates a task, in working days
  • O, optimistic: the time if things go unusually well.
  • M, most likely: the time you would bet on.
  • P, pessimistic: the time if things go badly.

The formula pulls the answer toward the likely case but keeps the risk. “Design the booth” has a likely time of 6, yet (4 + 4 × 6 + 14) ÷ 6 gives 7, because its bad case is so long.

For each task, ask what must be finished first, and write that in the “After” column. Then draw an arrow for each entry. “Train the booth team” comes after both C and E, so two arrows meet there. The network must not loop back.

Do the forward and backward pass

Each box has six numbers, with the earliest dates on top and the latest below:

The legend from the board: early start, duration and early finish on top, ID and task in the middle, late start, slack and late finish below.
How to read a task box

Go forward from day 0 and add each duration. When arrows meet, take the latest finish, because the task waits for everything before it. So G starts on day 14, when C is done, even though E finishes on day 5.

The network with only the top row of each box dark: early start, duration and early finish, such as 3, 7 d and 10 for task B.
Forward pass: the top row, left to right

Then go backward from the finish, day 21, and subtract. When arrows split, take the earliest start of what follows. Slack is the difference between late and early start.

The later tasks with only the bottom row of each box dark: late start, slack and late finish, such as 13, 3 and 17 for task D.
Backward pass: the bottom row, right to left

Find the critical path

Follow the tasks with zero slack: A, B, F, H and I. They add up to 3 + 7 + 7 + 2 + 2 = 21 working days, which runs Apr 5 to May 3.

The middle and end of the network with B, F, H, I and Finish in red, and C, D, E and G in black with slack of 2, 3, 11 and 2 days.
The red route sets the finish date

This tells you where effort pays off. Speeding up “Book travel and hotels”, with 11 days of slack, gains nothing. A day saved on “Build the booth” moves the finish, until another path becomes the longest.

What is the chance of finishing on time?

PERT also estimates spread. Each task’s standard deviation is (P − O) ÷ 6, and you combine those along the critical path. The board gets σ = 2.2 days, and “B adds the most doubt”. Finishing by day 24 comes out at about 91%.

Treat that as a rough guide. It looks only at the critical path, while C and G have just 2 days of slack and could overtake it. The real chance is a little lower.

Note also that a finish on May 3 leaves no margin before the show opens on May 4.

Drawing a PERT chart in FlowDraw

The template is free, in the Project management category.

The FlowDraw Templates page with PERT chart as the search result.
Find it under Templates in the sidebar
  1. Open the template

    Search for “PERT chart” under “Templates”, open the card, then choose “Use template”.

  2. Retype the estimates

    Double-click a table cell or any number in a box and type. Every number is plain text, so FlowDraw does no sums. Work them out by hand or in a spreadsheet, then type them in.

  3. Add a task

    Drag from an empty part of the board around a whole task box, which selects its 15 elements. Press ⌘D (Ctrl+D on Windows), drag the copy into place and retype it.

  4. Link it

    Press Esc, then L, and drag from one box to the next. The arrow stays attached when you move a box.

  5. Mark the critical path

    Click an arrow and pick red with “Line color” in “Line properties”. Click a task’s box and use “Stroke color” in “Shape properties”.

  6. Share the result

    Choose “Share” and add people, or use the “Embed” tab for a read-only copy that needs no account. “Export” gives you PNG, SVG, PDF or JSON.

The PERT chart template open in the FlowDraw editor, with the toolbar at the bottom and Share at the top right.
The template open in the editor

On Free, this board has 198 elements and Free holds 150. It opens whole and you can change every word, but adding anything is refused until you are under 150.

Deleting the title block, “How to read a task”, the critical path panel and one task box does it. Pro has no limit.

PERT chart mistakes to avoid

  • Three numbers that are really one. If O, M and P are close by habit, you lose the point. Ask what could go wrong.
  • Padding the most likely time. It counts four times in the formula, so the padding counts four times too.
  • Taking the earliest finish where arrows meet. The task waits for the last one, not the first.
  • Watching only the red path. A task with little slack, such as C here, can take over.
  • Reading 91% as a promise. It is only as good as the estimates behind it.
  • Never redoing the sums. When an actual time comes in, run both passes again.

FAQ

O is the optimistic estimate, if things go unusually well. M is the most likely. P is the pessimistic estimate, if things go badly. The expected time is (O + 4 × M + P) ÷ 6.

Continue Reading

A FlowDraw board with a refund process swimlane diagram: Customer, Support and Billing lanes, an Eligible? decision and a Refund in Stripe step.

Guides·

How to make a swimlane diagram

Learn how to make a swimlane diagram: what lanes and handoffs show, when one beats a flowchart, and how to draw it from a template or with AI.

A FlowDraw board with a sitemap for Learnly, an online course site: Home above six numbered sections, their pages below and a strip of global pages.

Guides·

How to create a website sitemap

A website sitemap shows every page and how pages nest. Learn how to plan one, how it differs from sitemap.xml and how to draw it from a free template.

A FlowDraw board with a BPMN diagram of order fulfilment: Customer and Store pools, Warehouse and Shipping lanes, and an In stock? gateway.

Guides·

How to create a BPMN diagram

Create a BPMN diagram with the symbols most processes need: events, tasks, gateways, pools and flows, explained through an order fulfilment example.

Ready to create your first diagram?

Turn your ideas, notes, or documents into a clear,
editable flowchart in seconds.

Get Started Free