What is a value stream map?
A value stream map follows one unit of work from request to delivery and records two kinds of time: the minutes someone spends working on it and the days it spends waiting. It comes from lean manufacturing, and it works as well for office processes, because the gap between the two numbers is where most improvement hides.
This template maps a refund at Linden Home, an online homeware store, from the customer’s request to money back. Process boxes hold the work, triangles hold the waiting, and a ladder under them adds up the lead time.
The flow: boxes, data and triangles
The map reads left to right. A customer asks for a refund, a line labeled “Refund form” carries the request to the help desk system (40 tickets a day), and five process boxes follow: Log request, Check order and photos, Approve refund, Send payment, Email customer. At the far right the customer gets the money back.
Under each process box is a data box with three figures. For “Check order and photos” they are C/T 10 min, People 3 and %C&A 80%. In front of each box is a triangle marked I, with the queue written beneath: 80 requests and 2 days wait before approval, 120 requests and 3 days before payment.
Two idea notes float above the flow at the steps they concern: “Auto-approve refunds under $50” and “Pay every day, not in a weekly batch”.
The timeline ladder
Below the flow, the ladder repeats the times on two levels. The upper level, Waiting, lists each queue: 0.5 days, 1 day, 2 days, 3 days, 0.5 days. The lower level, Working, lists each cycle time: 5, 10, 5, 15 and 5 minutes.
The box at the end of the ladder gives the totals. Lead time is 7 days, 40 min. Process time is 40 min. Rolled %C&A, the chance a refund passes every step right the first time, is 67%. One sentence sums it up: “Under 1% of the lead time adds value.”
A key under the ladder spells out the abbreviations, so a reader new to the notation is not lost.
Name the waste you see
A finished map should end in plain statements, and the “Waste spotted” panel shows how to write them. Each line names a kind of waste and points at the evidence on the map:
- Waiting: 7 days of queues around 40 minutes of work.
- Rework: 1 in 5 checks goes back for photos, which is the 80% under the second step.
- Batching: payments go out once a week.
Notice that none of them blames a person or a team. The waste is in how the work is arranged.
Sketch the future state
The panel beside it works out what the two idea notes would change. Auto-approving refunds under $50 cuts the 2-day wait before approval to half a day. Paying every day cuts the 3-day wait before payment to half a day. The last line states the new total: lead time of 3 days, 40 min, down from 7 days.
The process time does not move. That is typical: the quickest gains on a value stream map come from shrinking queues, not from asking people to work faster.
How to use the value stream map template
- Open the template as your own board. Rename the customer, the request and the five process boxes for your process; add or remove a box if it has more or fewer steps.
- Walk the process. Follow one real item from start to finish and write down what happens to it, not what the procedure says.
- Time each step and wait. Fill every data box and write the queue size and wait under every triangle.
- Draw the ladder. Copy the waits and cycle times onto the two levels, add them up yourself and type the totals.
- Mark the waste. Write three findings and one future-state estimate in the bottom panels.
For a longer walk-through of the method, read how to make a value stream map.
When to map a value stream, and when not to
Map a value stream when customers complain about how long something takes and nobody can say where the time goes. Refunds, quotes, onboarding, hiring and order fulfillment are all good subjects.
If the team has not yet agreed where the process starts and ends, draw a SIPOC first. If the delays come from handoffs between departments, a swimlane diagram shows who holds the work. To map what the customer sees alongside what staff do, use a service blueprint.
Questions about the Value stream map template
What is the difference between lead time and process time?
Lead time is the whole wait the customer experiences, from request to delivery. Process time is only the time someone is actively working on the item. In the example the lead time is 7 days and 40 minutes, and the process time is the 40 minutes.
What does %C&A mean on a value stream map?
Percent complete and accurate: the share of items a step passes on that the next step can use without sending anything back. Multiply the figures for every step to get the rolled value, which is 67% for the five steps in the example.
Is value stream mapping only for manufacturing?
No. It started on factory floors, but any process with requests, handoffs and queues can be mapped. The template’s example is office work: a refund moving through a help desk, an approval and a payment run.
How do you measure the waiting time between steps?
Count the items in the queue and divide by daily demand. With 40 requests a day, 80 requests waiting for approval means a wait of 2 days, which is exactly what the example writes under its third triangle.