What is a burndown chart?
A burndown chart shows how much work is left in a sprint, day by day. The line starts at the amount the team committed to and should reach zero on the last day. One look tells you whether the sprint is on pace, and it tells you early enough to do something about it.
This template has the chart, a panel of six numbers and a place for daily notes. The example is Sprint 9 of a team building an invoicing app: Mar 1 to 12, 2027, 32 points committed, and the header already says “Behind the ideal line”.
Two lines: ideal and actual
The chart is titled “Points left at the end of each day”. The vertical axis counts points, from 0 to 40. The horizontal axis counts working days, from Day 0, the start, to Day 10 on Mar 12. Weekends are skipped, so Day 5 is Mar 5 and Day 6 is Mar 8.
The ideal line is dashed and straight. It runs from 32 points at the start to 0 on Day 10, the path of a team that closes the same amount every day. The actual line is solid, with a dot for each day that has ended. When the dots sit above the dashed line, the team is behind. Below it, ahead.
What the shape of the line tells you
The first five days of the example hold three lessons.
- A flat start. After Day 1 the line is still at 32. Nothing was closed, usually because the stories are too big to finish in a day.
- A steady drop. Days 2 and 3 take it to 29 and then 26. This is what progress looks like.
- A jump up. On Day 4 the line climbs back to 29, and a label says “+5 points added”. Work did not come undone. Scope came in during the sprint.
A burndown that never moves up is not always a calm sprint. Sometimes it is a chart nobody is honest with. Mark added work where it happens.
The forecast: where the sprint will end
A red line marks today, Day 7. The last dot stands at 18 points, while the ideal line has fallen to about 10. From that dot, a second dashed line carries the recent pace forward to the end of the sprint and stops at a label: “About 7 left”.
The note in the side panel gives the arithmetic: “Pace: 3.7 points a day for the last three days. At that pace about 7 points are left on Mar 12.” The forecast uses the last three days instead of the whole sprint because the recent pace says more about the days to come than a slow first day does.
Six numbers that explain the chart
The panel “Sprint 9 so far” puts the chart into numbers: Committed 32, Added +5, Done 19, Left 18, Days left 3 and Needed a day 6.0. They check each other: 32 plus 5, minus 19 done, leaves 18.
The last tile is the one to act on. Finishing 18 points in 3 days needs 6.0 a day, and the team has been closing 3.7. No amount of effort closes a gap that size, so the conversation moves to scope: what comes out of the sprint?
How to use the burndown chart template
- Open it on a new board. Use this template gives you Sprint 9 as a starting point.
- Draw the ideal line. Relabel the axes for your sprint length and your commitment, then run the dashed line from that number down to zero on the last day.
- Log points left daily. At the end of each day, place a dot at the points still open and extend the solid line to it. Update the six tiles.
- Note what changed. One line for any day the chart surprises you, as in “Day 4: +5 points: urgent invoice totals fix.”
- Act early. When the forecast misses, name what goes. The Day 7 note does: “Drop Bulk edit (3) unless started Day 8.”
When a burndown chart fits
It fits a team that works in fixed sprints and estimates its work, in points, hours or a plain count of tasks. Show it at the daily meeting and again at the review.
The chart needs a commitment to burn down, which comes out of sprint planning. It says how much is left, not which stories are stuck: a scrum board answers that. For work that runs on dates and dependencies instead of sprints, a Gantt chart is the better picture.
Questions about the Burndown chart template
What does it mean when a burndown line goes up?
Work was added to the sprint, or an estimate was raised. In the example the line climbs on Day 4 because an urgent fix worth 5 points came in. Label every rise on the chart so nobody mistakes it for lost progress.
How do I update the chart each day?
Count the points still open at the end of the day, place a new dot at that height in the day’s column and extend the line to it. The chart is a drawing, so the dot goes where you put it. It takes about a minute.
Should we burn down story points, hours or tasks?
Use whatever the team already estimates in. Points work well when stories differ a lot in size. If your tasks are all small, counting tasks is simpler and just as useful. Change the axis title and the numbers to match.
What is the difference between a burndown and a burnup chart?
A burndown plots work left and falls toward zero. A burnup plots work done and rises toward the total, with the total drawn as its own line. Burnup shows scope changes more clearly; burndown is quicker to read in a daily meeting.