Gantt chart template

Fourteen rows, three milestones and a today line, drawn for a 12-week website relaunch. Put in your own tasks and dates and see in one look what is behind.

The Gantt chart template

What is a Gantt chart?

A Gantt chart lists a project’s tasks down the left and draws each one as a bar on a calendar. The bar starts on the task’s start date and stops on its finish date, so you read the length of the work and the order of the work in one look. It is named after Henry Gantt, the engineer who made the format popular.

This template pairs a task table with twelve weekly columns. It is filled in for a website relaunch: 14 rows, Jan 4 to Mar 26, 2027, run by a project manager called Maya. For more on drawing schedules in FlowDraw, see the Gantt chart page.

The Gantt chart template: a task table on the left and bars across twelve weeks of January, February and March on the right.
The whole board: the table names the work, the calendar shows when it happens.

The task table

The left side is a table with six columns: a number, the task, its owner, start, finish and how much is done. One row holds one task, and a task has one owner. “Content audit” belongs to Sam and runs Jan 11 to Jan 15. “Visual design” belongs to Leo and runs Feb 1 to Feb 12.

Three rows have no start date: “Scope signed off” on Jan 15, “Design approved” on Feb 12 and “Go live” on Mar 22. These are milestones. A milestone is a moment, not a stretch of work, so it carries only a finish date. The last filled row says “Add a task” and waits for yours.

Milestone rows such as Scope signed off have a finish date and no start.

Bars, diamonds and arrows

The right side is the calendar. Three months sit across the top, and under them one column for each week, labelled with its Monday: 4, 11, 18, 25. A bar covers the weeks its task runs. A diamond marks a milestone on its date.

Arrows show order. Each one leaves the task that must finish first and points at the task that waits for it. “Sitemap and wireframes” ends on Jan 29 and feeds three tasks that all start on Feb 1: visual design, CMS setup and content writing. “Go live” has two arrows coming in, from “QA and accessibility” and from “Redirects and SEO”, so it cannot happen until both are finished.

The legend under the chart names every mark: planned, done, behind plan, milestone met, milestone ahead, today and must finish first.

One week is one column, so a two-week task is a bar two columns wide.

Read the chart at the today line

A red vertical line marks today, Feb 18 in the example. Inside each bar a darker fill shows the share that is done, the same number as the Done column. The reading rule is short: everything left of the line should be filled.

“Page templates” started on Feb 15 and is 20% done, which is fine a few days in. “Content writing” is the problem. It runs Feb 1 to Feb 26 and stands at 50% with about a week left, so its bar is amber and the header says “1 task behind plan”. Follow its arrow to see what is at stake: “Content migration” starts on Mar 1 and needs that writing.

The amber bar is half filled although most of its time has passed.

How to use the Gantt chart template

  1. Open it as a new board. Use this template copies the website relaunch into your workspace so you can edit it row by row.
  2. List the tasks. Replace the 14 rows with your own. Keep a task between a few days and three weeks, and give every approval a milestone row.
  3. Set dates and owners. Type the start and finish, then drag each bar so it covers those weeks. The table and the bars are separate parts of a drawing, so change both.
  4. Link dependencies. Draw an arrow from the end of the task that must finish first to the start of the task that waits.
  5. Track progress. Once a week, move the today line, update the Done column and stretch the darker fill to match.

The guide How to make a Gantt chart covers the method in more depth.

The four steps are printed above the chart, next to the project’s dates and status.

When a Gantt chart fits, and when to pick another

A Gantt chart fits when the tasks have dates, the order matters and someone will update it every week. Ten to thirty rows is the comfortable range.

If your audience only needs the phases and a few key dates, a project timeline says it with far less detail. If the dates are fixed and you only want to watch them slip or hold, use the milestone tracker. If you are still unsure how long tasks will take and want to find the chain that decides the end date, start with a PERT chart and draw the Gantt chart afterwards.

Questions about the Gantt chart template

Is the Gantt chart template free?

Yes. The board has 128 elements and a Free board holds up to 150, so it opens on the Free plan with room for a few more bars. A much longer schedule needs the Pro plan.

Do the bars move when I change a date in the table?

The table and the bars are separate elements of one drawing. When a date changes, edit the cell and drag or resize the bar so it covers the right weeks. Doing both takes a few seconds and keeps the two sides telling the same story.

What is the difference between a task and a milestone?

A task takes time and has a start and a finish, like the two weeks of visual design. A milestone takes no time: it is the moment something is decided or delivered, like the design being approved on Feb 12. Draw it as a diamond.

How many dependencies should I draw?

Only the real ones: an arrow means the later task cannot start without the earlier one. If every bar is linked to every other, the arrows stop telling you anything. In the example most tasks have one arrow in and one out.