What is a dependency map?
A dependency map shows which pieces of work wait for which. When several teams build one thing, each team’s plan can look fine by itself and still fail, because team B needs something in sprint 3 that team A will finish in sprint 4. A dependency map puts those links on one page so they are found in planning, not in the sprint.
This template is a grid for one quarter. The example is called Checkout rebuild: five teams, six two-week sprints from January to March 2027, eleven pieces of work and eight arrows between them. Two of the arrows are trouble, and the board shows how to mark and fix them.
The grid: teams down, sprints across
Each row belongs to a team and names its lead: Platform (Ravi), Payments (Kim), Web (Ola), Mobile (Sean) and Data (Elena). Each column is a sprint with its dates, from Sprint 1 on Jan 4 to Sprint 6 ending Mar 26. A box sits in the sprint where its team plans to finish it. The Payments row, for example, has the payment provider contract in Sprint 1, the Saved cards API in Sprint 2 and the Refunds API in Sprint 5.
A thin row above the teams holds the milestones as black dots: “Beta for 5% of shoppers” at the end of Sprint 4 and “Launch to everyone” at the end of Sprint 6. They tell you which boxes cannot move right without moving a date the business cares about.
Arrows mean “needed by”
An arrow runs from a piece of work to the work that needs it. Read the left of the example: the Saved cards API needs two things from Sprint 1, the single sign-on service from Platform and the payment provider contract. In turn, two things in Sprint 3 need the API: the Checkout page on Web and the Checkout screens on Mobile.
A healthy arrow points to the right and crosses at least one sprint line. That gap is the room for the first team to finish before the second starts. The board’s own instructions name the two patterns to look for: arrows that point back in time, and arrows that stay in one sprint.
At risk and in conflict
The example marks two problems with color. The Saved cards API is amber, at risk: it is slipping into Sprint 3, the sprint where the page and the screens need it. Its two outgoing arrows are amber too, so you can follow the damage downstream.
The Refund status screen on Mobile is red, a conflict. It is planned in Sprint 5, the same sprint as the Refunds API it needs, and the arrow between them goes straight down the column. Nothing has slipped yet. The plan itself cannot work as drawn, and that is the kind of problem a dependency map exists to catch.
A key and a note for every problem
Under the grid a key explains the four box styles, Done, Planned, At risk and Conflict, plus the arrow (“Needed by”) and the milestone dot. Green boxes such as the single sign-on service are finished and need no more attention.
Below the key, every colored box gets a note that says what is wrong and what happens next. The amber note ends “Kim confirms by Jan 22”. The red note gives the fix: “Move it to Sprint 6.” A map with red boxes and no notes only reports trouble. The note is what turns it into a decision with a name or a date on it.
How to use the dependency map template
- Open it as a new board. Use this template copies the checkout example into your workspace.
- Place the work. Rename the rows to your teams and the columns to your sprints or months. Ask each lead to drop their own boxes into the sprint where the work will be finished.
- Draw what needs what. Go box by box and ask “what must exist before this can start?” Draw an arrow from each answer to the box.
- Flag the risks. Recolor any box whose arrow stays in one column or points left, and any box that feeds a milestone with no sprint to spare.
- Agree the fixes. For each flagged box, move it, split it or accept the risk, and write the outcome in a note with a name and a date.
When to map dependencies, and when not to
Draw one at quarterly or release planning, whenever more than two teams contribute to the same outcome. It is also useful after a missed date, to see which link broke.
The map shows order between teams. It does not show how long anything takes. If you need durations and the longest chain of tasks, use a PERT chart, and for dates on a calendar, a Gantt chart. If the question is which features ship in which release, the release plan is the closer fit.
Questions about the Dependency map template
What counts as a dependency?
Anything one team needs from another before it can start or finish: an API, a design, a signed contract, a decision, test data. In the example even a payment provider contract is a box, because the Saved cards API cannot be built without it.
How detailed should the boxes be?
One box per thing another team could wait for. Stories inside a single team do not belong here. The example has eleven boxes for a whole quarter of five teams, and that is about as much as people can read in a planning meeting.
What do I do with a dependency inside the same sprint?
Treat it as a conflict. Move the work that waits to a later sprint, as the example does with the refund status screen, or split the first piece so the part others need is ready early in the sprint.
How often should the map be updated?
At the end of every sprint. Turn finished boxes green, move anything that slipped, and check each moved box’s outgoing arrows. A box that moves right can turn a healthy arrow into a conflict.