What is a PERT chart?
PERT stands for program evaluation and review technique. A PERT chart draws a project as a network: every task is a box, and arrows join the boxes in the order the work must happen. With a duration on each box you can work out two things a plain task list hides: the earliest day the project can finish, and which tasks have no room to slip.
This template holds a network of nine tasks, a table of estimates, a panel for the critical path and a key that explains the numbers. The example is a team getting a booth ready for a trade show, starting on Apr 5 and finishing on May 3.
The network: tasks and the arrows between them
The network reads from left to right. Work begins with A, “Confirm booth and budget”. When A is done, three tasks can start at once: B “Design the booth”, C “Build the demo app” and E “Book travel and hotels”. That is a split.
Further right the paths join again. H “Ship the booth” has two arrows coming in, from D “Print brochures and banners” and from F “Build the booth”, so it waits for whichever ends later. The last task, I “Set up and rehearse”, waits for both G and H. A join is where delays collect, and a PERT chart makes every join visible.
How to read a task box
Each box carries six numbers around the task’s name. The key spells them out: early start, duration and early finish on top, late start, slack and late finish underneath. In the board’s words, “Top: earliest dates. Bottom: latest dates.”
Take C, “Build the demo app”. Its top row reads 3, 11 d, 14: it can start on day 3 and end on day 14. Its bottom row reads 5, 2, 16: it may start as late as day 5 and end on day 16 without holding anything up. The middle number, 2, is its slack.
Three rules beside the key say where the numbers come from. Forward pass: early start is the latest early finish before the task. Backward pass: late finish is the earliest late start after it. Slack is late start minus early start.
Three estimates for every task
Nobody knows exactly how long a task will take, so PERT asks for three guesses: O, the optimistic one, M, the most likely, and P, the pessimistic one. The table blends them with the formula printed above it: Expected = (O + 4 × M + P) ÷ 6.
B “Design the booth” has 4, 6 and 14 days. The expected value is 7 days, a day more than the most likely guess, because the bad case is much further away than the good one. H “Ship the booth” has 2, 2 and 2: nobody doubts how long shipping takes. The spread between O and P is worth reading for itself. A wide spread marks the tasks to worry about.
The last column, After, lists what each task waits for. It is the same information as the arrows, in a form that is easier to check.
The critical path
Tasks with zero slack form the critical path: the longest chain through the network, and the one that sets the finish date. The panel names it, “A → B → F → H → I”, and gives its length: “21 working days, Apr 5 to May 3.” The next line shows why that matters: “The show opens on May 4.” A one-day delay anywhere on that chain costs the opening.
The card beside it uses the spread of the estimates: “Chance to finish by day 24: About 91%”, with the remark that B adds the most doubt. That points the team at one task. If the booth design can be made more certain, the whole plan gets safer.
How to use the PERT chart template
- Bring it into your workspace. Use this template makes an editable copy of the trade show network.
- Estimate each task. List your tasks in the table, give each an O, M and P in working days and work out Expected with the formula.
- Link the tasks. Fill the After column, then draw one arrow for every entry in it.
- Forward and backward pass. Write early start and early finish from left to right. Then write late finish and late start from right to left, and subtract to get slack.
- Find the critical path. Highlight the boxes with zero slack. The others can move: E “Book travel and hotels” has 11 days of slack.
The numbers are text on the board, so repeat the two passes when an estimate changes. The guide How to make a PERT chart walks through both.
When a PERT chart is worth the effort
Draw one when durations are uncertain and tasks depend on each other in more than a straight line: an event, a launch, a move. For a project that is one chain of tasks, it tells you nothing new.
PERT works in day numbers, not calendar weeks. Once the path is clear, a Gantt chart shows the same tasks against dates and is easier to update. If you only need to see which team waits for which, a dependency map is lighter. And if the task list itself is in doubt, start with a work breakdown structure.
Questions about the PERT chart template
What is the critical path in a PERT chart?
It is the longest chain of dependent tasks from start to finish. Its length is the shortest time the project can take, and every task on it has zero slack. In the example the path runs through five tasks and lasts 21 working days.
What is the difference between a PERT chart and a Gantt chart?
A PERT chart is a network that shows order and slack, and it handles uncertain durations with three estimates. A Gantt chart is a calendar that shows each task as a bar with dates. Use PERT to plan and find the critical path, then Gantt to track the work week by week.
Why give three estimates instead of one?
One number hides how sure you are. Three numbers show the range, and the formula leans toward the most likely value while still counting the bad case. Tasks with a wide range, like the booth design at 4 to 14 days, are where the plan is fragile.
Can I use the PERT chart template on the Free plan?
The template has 198 elements, more than the 150 a Free board holds, so it needs the Pro or Team plan. A network of nine tasks uses many small parts: six numbers, a name and several lines for every box.